Mission Beach Aquatic Facility

Cassowary Coast Regional Council has been working with the local Mission Beach community for over fifteen years to make the Mission Beach Aquatic Facility a reality. Jointly funded by the Australian Government through the National Stronger Regions Fund, the Queensland Government's Building our Regions program, and the Mission Beach Aquatic and Recreation Club Inc., the facility will include a six-lane, 25m lap pool, a recreational billabong-style pool and a hydrotherapy pool. The facility will have a rainforest theme in keeping with its setting in MARCS Park.

Look at some sketches

Look at some plans and download some sketches

Early works are already underway, with the main construction activities commencing in early 2017. Completion is currently scheduled for December 2017. Get your togs ready to be swimming in the steamy months of early 2018!


This project is proudly funded by the Australian Government through the National Stronger Regions Fund and the Queensland Government's Building our Regions program.

Cassowary Coast Regional Council has been working with the local Mission Beach community for over fifteen years to make the Mission Beach Aquatic Facility a reality. Jointly funded by the Australian Government through the National Stronger Regions Fund, the Queensland Government's Building our Regions program, and the Mission Beach Aquatic and Recreation Club Inc., the facility will include a six-lane, 25m lap pool, a recreational billabong-style pool and a hydrotherapy pool. The facility will have a rainforest theme in keeping with its setting in MARCS Park.

Look at some sketches

Look at some plans and download some sketches

Early works are already underway, with the main construction activities commencing in early 2017. Completion is currently scheduled for December 2017. Get your togs ready to be swimming in the steamy months of early 2018!


This project is proudly funded by the Australian Government through the National Stronger Regions Fund and the Queensland Government's Building our Regions program.

  • Mission Beach Aquatic Centre - Project Update - September 2017

    3 months ago
    21077423 10155381236855733 8653046240634223056 n

    Early works are now 100% complete. We had a delay due to the tender being extended from the 2nd December to 12th December to enable subcontractors more time to price items for tenderers.

    The building contractor AJ Homes received possession of site on the 28th April 2017.

    The major construction works are now under way with the first concrete pour completed. The first stages scheduled for completion are the pumproom and the earthworks for the billabong pool. Billabong pool is formed and concrete poured.

    The project is now at 50% complete... Continue reading

    Early works are now 100% complete. We had a delay due to the tender being extended from the 2nd December to 12th December to enable subcontractors more time to price items for tenderers.

    The building contractor AJ Homes received possession of site on the 28th April 2017.

    The major construction works are now under way with the first concrete pour completed. The first stages scheduled for completion are the pumproom and the earthworks for the billabong pool. Billabong pool is formed and concrete poured.

    The project is now at 50% complete and running as per scheduled.


  • Project Update - November 2016

    about 1 year ago
    Mbaf masterplan

    Welcome to the first Mission Beach Aquatic Facility Project Update. As we move into the main construction phase of the project, these very brief project updates will be issued at regular intervals to keep you up to date with what's happening and when.

    · The tender period for the Principal Contractor for the project has been extended with the contract now expected to be awarded at the Local Government meeting in January 2017. The extension will give contractors submitting a tender more time to work with subcontractors to ensure proposals submitted provide the best value for money possible.

    · Main construction works will begin in early 2017.

    · Early works are well underway with the placement of gabions for the retaining wall on the oval side of the driveway and installation of the Ergon pad still to be completed.

    Welcome to the first Mission Beach Aquatic Facility Project Update. As we move into the main construction phase of the project, these very brief project updates will be issued at regular intervals to keep you up to date with what's happening and when.

    · The tender period for the Principal Contractor for the project has been extended with the contract now expected to be awarded at the Local Government meeting in January 2017. The extension will give contractors submitting a tender more time to work with subcontractors to ensure proposals submitted provide the best value for money possible.

    · Main construction works will begin in early 2017.

    · Early works are well underway with the placement of gabions for the retaining wall on the oval side of the driveway and installation of the Ergon pad still to be completed.